Mine Tailings Drain Installed at New England Superfund Site

Posted on

Late summer DTD completed the successful installation of a gravity drain in a mine tailings impoundment at the Callahan Mine…


Ulster Wetland Crossing – 2,300′ of 6″

Posted on

In early February, DTD initiated a 2,300′ long bore near Ulster, PA.  The bore was to cross under a wetland…


Sugar Creek Crossing – 1,700′ of 8″

Posted on

This crossing initially was designed to be approximately 900 feet long, passing near a shallow residential well, then 30 feet…


DTD has recently added a large mud recycling system to its fleet of equipment.

Posted on

DTD has recently added a large mud recycling system to its fleet of equipment. The Mud Tech International system has…


DTD publishes article on benefits of biopolymer drilling fluids.

Posted on

DTD publishes article on benefits of biopolymer drilling fluids.


DTD completes DC dewatering wells despite blizzard conditions.

Posted on

DTD recently completed a series of six dewatering wells to support construction of the DC to Dulles Metrorail in Washington,…


DTD Updates Air Sparge Spreadsheet

Posted on

DTD’s free downloadable spreadsheet that selects slotting patterns to effectively distribute air flow evenly across air sparge horizontal wells has…


DTD has completed the installation of a well at a EPA Superfund Site

Posted on

The well design (very low screen open area and multiple casings) required the use of our American Augers 210,000 lbs-rated…


EPA’s July 2009 press release features a DTD installed air sparge well

Posted on

The final results show the strength of appropriate use of horizontal air sparge wells for groundwater remediation. Not only did…


DTD publishes new Glossary of HDD Terminology

Posted on

Since many practitioners are new to horizontal directional drilling in environmental applications, they are often unfamiliar with the specialized terminology…