In December 2018, DTD installed a dual purpose horizontal well as part of a remediation pilot test at a chemical…
DTD is beginning 2018 with the three bores for pipeline installation in the Midwest. The crossings trend beneath a small…
Client demands for ever-longer wells continues to push the limits of what can be accomplished using HDD to install horizontal…
DTD recently completed the installation of two 850′ long horizontal sparge wells in Southern Ohio. Understanding the local geology on…
When we think of unforeseen challenges of horizontal drilling, we usually think of challenges underground; fractured rock, gravel and cobble, lost drilling mud,…
Heading back to the southwest after the holiday break, DTD completed the installation of a horizontal remediation system in the…
DTD has completed the installation of an 860 foot, 4-inch diameter steel pipeline beneath an extensive wetland and small headwaters…
This Spring DTD completed the installation of an 1,130′ horizontal remediation well using our patent pending Knock Off Technology. The…
DTD completed the installation of a short utility boring that crossed beneath a small street and multiple existing utilities. Total length…
DTD has recently completed a small scale project near Little Rock, AR. Plans for bettering the subsurface conditions included two dual phase…